C_TS412_2021 Exam Question 1

You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
  • C_TS412_2021 Exam Question 2

    You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
  • C_TS412_2021 Exam Question 3

    What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
  • C_TS412_2021 Exam Question 4

    When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.
  • C_TS412_2021 Exam Question 5

    Which object is relevant in assembly processing to create an assembly order for the SD document?