C_TS412_2021 Exam Question 11

What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
  • C_TS412_2021 Exam Question 12

    Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
  • C_TS412_2021 Exam Question 13

    To which object can you assign a factory calendar?
  • C_TS412_2021 Exam Question 14

    You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
  • C_TS412_2021 Exam Question 15

    An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?