C_TS412_2021 Exam Question 21

Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
  • C_TS412_2021 Exam Question 22

    What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
  • C_TS412_2021 Exam Question 23

    How are earliest dates and latest dates of activities scheduled?
  • C_TS412_2021 Exam Question 24

    What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
  • C_TS412_2021 Exam Question 25

    In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?