AgilePM-Practitioner Exam Question 1
Towards the end of the Foundations phase of Project Increment 4, with the high-level requirements agreed, Hira, has asked the Developers to estimate the work required to deliver the Eco spa solution.

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.
What should the Developers do to help Hira make this decision?)

(The Developers have used the Planning Poker technique to generate their estimates. Hira now needs to determine how many Sprints will be required for the Delivery Teams to deliver the Eco-spa.
What should the Developers do to help Hira make this decision?)
AgilePM-Practitioner Exam Question 2
Which 2 actions should the Technical Coordinator take to implement the new Must Have requirement?
AgilePM-Practitioner Exam Question 3
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
AgilePM-Practitioner Exam Question 4
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance Manager that it was a fixed price for a fixed specification' project. The Project Manager has decided that the best way to tackle it would be to leave the development of the least valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
Decide if each observation is an appropriate application of Agile Project Management for this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance Manager that it was a fixed price for a fixed specification' project. The Project Manager has decided that the best way to tackle it would be to leave the development of the least valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
AgilePM-Practitioner Exam Question 5
Which 'event' BEST offers the opportunity to connect learning to the wider change initiative?