CTAL-TM_Syll2012 Exam Question 46

Testing Process
Assume you are the Test Manager for a new software release of an e-commerce application.
The server farm consists of six servers providing different capabilities. Each capability is provided through a set of web services.
The requirements specification document contains several SLAs (Service Level Agreements) like the following:
SLA-001: 99.5 percent of all transactions shall have a response time less than five seconds under a load of up-to 5000 concurrent users The main objective is to assure that all the SLAs specified in the requirements specification document will be met before system release. You decide to apply a risk-based testing strategy and an early risk analysis confirms that performance is high risk. You can count on a well-written requirements specification and on a model of the system behavior under various load levels produced by the system architect.
Which of the following test activities would you expect to be the less important ones to achieve the test objectives in this scenario?
Number of correct responses: 1
K4 3 credits
  • CTAL-TM_Syll2012 Exam Question 47

    Defect Management
    Consider a defect report and assume that a part of its lifecycle includes the following states:
    New: Is the initial state
    Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect
    Closed: is the final state
    Which of the following answers represents an invalid sequence of states that can't lead the bug report to the "Closed" state?
  • CTAL-TM_Syll2012 Exam Question 48

    You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops.
    You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testinG.
    EXCR1- Each "critical" quality risk item must be covered by at least one test condition
    EXCR2- Each "critical" requirement must be covered by at least one test condition
    The following are the "critical" requirements of the application:
    REQ-SEL-1. The application shall allow the user to order only one package at a time
    REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles, 6-bottles, 12-bottles, 15-bottles)
    REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size)
    REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size)
    REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa, MasterCard, American Express)
    REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card data are given by the user
    The following is the unique "critical" quality risk item that has been identified:
    CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user Test analysis for system testing has just begun and the following test conditions have been identified.
    TC-SEL-2. Test the selection of the package sizes
    TC-SEL-4. Test wrong numbers of bottles for an order
    TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
    What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and EXCR2 exit criteria?
    K3 2 credits
  • CTAL-TM_Syll2012 Exam Question 49

    Assume you are managing the system testing execution phase of a project.
    The system test execution period for that project is scheduled for eighteen weeks and the release date is scheduled at the end of system testing.
    During the sixth week of system test execution, at the staff meeting, the project manager informs you that the project deadlines are changed and the release date that is only three weeks ahead.
    This new release will not allow the completion of the system tests. Suppose also that you have followed a risk-driven test approach for this project.
    Which of the following statements represents the worst way to lead your test team in the next three weeks?
    K2 1 credit
  • CTAL-TM_Syll2012 Exam Question 50

    Reviews
    Which of the following factors could negatively influence a review?