PMI-RMP Exam Question 71

A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
  • PMI-RMP Exam Question 72

    During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.
    How should the risk manager address this concern?
  • PMI-RMP Exam Question 73

    A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.
    What should the risk manager do next to visually organize the risks?
  • PMI-RMP Exam Question 74

    There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.
    What should the risk manager do to resolve this recurring situation?
  • PMI-RMP Exam Question 75

    During project planning, a risk is identified for which the risk manager has defined a mitigation strategy.
    Later during project execution, this risk still leaves substantial residual risk.
    What should the risk manager do to handle this situation?