PMI-RMP Exam Question 76

A mega facility development project is evaluating some options to achieve the project schedule and budget.
Each option's success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
  • PMI-RMP Exam Question 77

    A project manager wants to introduce a new technology to improve a project's performance. However, there are some costs associated that are beyond the current budget, and the proposed technology has not been applied to any previous company projects.
    What should the project manager do in this situation?
  • PMI-RMP Exam Question 78

    While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?
  • PMI-RMP Exam Question 79

    A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
    What should the risk manager do first?
  • PMI-RMP Exam Question 80

    Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
    How should the risk manager proceed?