PMP Exam Question 131

The Project Manager is reviewing testing output. Generally, the data looks good. He does observe seven consecutive data points on one side of the mean in a couple of areas on the control chart.
What is this called?
  • PMP Exam Question 132

    A prevents action is approved by the change control board (CCB). What should the project manager do next?
  • PMP Exam Question 133

    A company has a longstanding client who is often late with payment. The company now has a new project with this client. What document should the project manager use to ensure that payment delay information is documented for this project?
  • PMP Exam Question 134

    Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it cohosted the 10K run through Overland Pass. Which of the organizational process assets might be helpful to you on your new project?
  • PMP Exam Question 135

    When managing a project team, what helps to reduce the amount of conflict?