PMP Exam Question 146
A project's latest earned value (EV) report indicates that a certain task has an estimate at completion (EAC) of US$550,000 and a budget at completion (BAC) of US$500,000. What should the project manager experience with this task?
PMP Exam Question 147
During the implementation phase of a construction project the customer asked a key subcontractor to deliver a work package ahead of time The subcontractor was not prepared for it and asked the project manager for additional budget What should the project manager do first?
PMP Exam Question 148
You have completed the Information Distribution Process and are now in a position to make needed information available to project stakeholders in a timely manner. All the following could be outputs from Information Distribution EXCEPT:
PMP Exam Question 149
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
PMP Exam Question 150
After preparation of the project management plan, the project manager schedules a meeting with key stakeholders. What part of the project will this complete?