PMP Exam Question 86
Which of the following is a schematic display of the project's schedule activities and the logical relationships among them?
PMP Exam Question 87
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process, What should the project manager do?
PMP Exam Question 88
Due to a lack of experience, a team is unable to commit to meeting the approaching data for milestone. What should the project manager do to milestone data?
PMP Exam Question 89
You are project manager responsible for constructing a new sports arena for the upcoming Olympics. Construction began on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You've obtained the following measurements:
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5
Based on the measurements above, which of the following statements are TRUE?
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5
Based on the measurements above, which of the following statements are TRUE?
PMP Exam Question 90
Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.