PMP Exam Question 76
A project deadline is fast approaching, and the team suggests skipping internal quality checking and testing to meet it. What should the project manager do?
PMP Exam Question 77
The reason that the schedule performance index (SPI) is shown as a ratio is to______________
PMP Exam Question 78
The concrete for a project arrives on time, but the project manager discovers that the concrete's composition is incorrect. What document should the project manager review to verify the concrete's performance and quality requirements?
PMP Exam Question 79
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
PMP Exam Question 80
Which of the following is the primary output of the Identify Risks process?