PMP Exam Question 556

Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except for which one?
  • PMP Exam Question 557

    A project manager is finalizing the stakeholder engagement plan. The project manager refers to the lessons learned register and discovers that there were issues in communicating with one stakeholder that is involved with this project None of the approaches to engage this stakeholder yielded an optimal result What should the project manager do?
  • PMP Exam Question 558

    After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features What should the project manager do to avoid this in the future?
  • PMP Exam Question 559

    A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.
    How should the project manager ensure that project risks are reported accurately in the risk register?
  • PMP Exam Question 560

    A team of experts provides a project manager with different effort estimates for implementing a project's scope. What tool or technique should the project manager use to develop a project schedule?