PMP Exam Question 146

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
  • PMP Exam Question 147

    You are managing a complex construction project for your organization. As part of your Resource Management Plan, you are creating a bar chart illustrating the amount of time that a resource is scheduled to work over a period of time. This chart is also known as:
  • PMP Exam Question 148

    You've been hired as manager to design and construct a new casino in Las Vegas, over the next 18 months. Given the size of the project and the abbreviated time frame, you are attempting to identify ways to reduce the timeframes for many of various tasks. You've developed the WBS and created a Gantt chart using specialized scheduling software.
    After analyzing the data, you've discovered several opportunities where tasks and phases may be overlapped in order to save time. This is an example of:
  • PMP Exam Question 149

  • PMP Exam Question 150

    Lessons learned documentation is gathered during which of the following Project Management Process Groups?