PMP Exam Question 156
Inputs to the Plan Risk Management process include the:
PMP Exam Question 157
A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.
What should the project manager do to address this situation?
What should the project manager do to address this situation?
PMP Exam Question 158
A project has five activities: A-B-C-D-E. All are finish-to-start (FS). Activity duration and order of implementation are as follows:
Activity A has a duration of one day. Activity B follows A and takes five days Activity C follows B and takes two days. Activity D follows B and A and takes two days. Activity E is preceded by C and D and takes two days.
What are the total float and free float days for activity D?
Activity A has a duration of one day. Activity B follows A and takes five days Activity C follows B and takes two days. Activity D follows B and A and takes two days. Activity E is preceded by C and D and takes two days.
What are the total float and free float days for activity D?
PMP Exam Question 159
The document that describes how the project scope will be defined, documented, validated, managed, and controlled, called:
PMP Exam Question 160
A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing Which three corrective actions should the project manager perform? (Choose three)