PSM-I Exam Question 56
The CEO asks the Development Team to add a "very important" item to a Sprint that is in progress. What should the Development Team do?
PSM-I Exam Question 57
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose the best two answers.)
PSM-I Exam Question 58
Who is on the Scrum Team? (Choose all that apply.)
PSM-I Exam Question 59
Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)
PSM-I Exam Question 60
If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?