PSM-I Exam Question 36

How should a Development Team deal with non-functional requirements?
  • PSM-I Exam Question 37

    Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
    A good way to continue is:
  • PSM-I Exam Question 38

    A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
  • PSM-I Exam Question 39

    Which three purposes does the definition of "Done" serve? (Choose three.)
  • PSM-I Exam Question 40

    True or False: When multiple teams work together on the same product, each team should maintain a separate Product Backlog.