LEED-AP-BD-C Exam Question 111

An HVAC system consists of an air handler supplying conditioned air (mixture of return air and outdoor air) to an office, corridor, conference room and lobby. For Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance, the ventilation rate procedure calculations must be based upon what HVAC system configuration?
  • LEED-AP-BD-C Exam Question 112

    During the early stages of a LEED for Schools project, the team was able to reduce the number of lighting fixtures in classrooms by 25% because the project team selected paint color whose light reflectance value was 75% instead of the initially proposed 64% value. This strategy is an example of applying which of the following credits to the project?
  • LEED-AP-BD-C Exam Question 113

    A project team compares a life-cycle assessment (LCA) model to a baseline design to determine the reductions in six impact categories. One impact category exceeds the baseline by 7%. Which alternative analyses should the team run to check different impact measurements?
  • LEED-AP-BD-C Exam Question 114

    Which rating system is being used if all of the credits below have been submitted towards certification?
    - Location and Transportation Credit, Reduced Parking Footprint
    - Energy and Atmosphere Credit, Fundamental Refrigerant Management
    - Indoor Environmental Quality Credit, Acoustic Performance
    - Materials and Resources Credit, Persistent, Bio accumulative, and Toxic (PBT) Source Reduction - Lead, Cadmium, and Copper
  • LEED-AP-BD-C Exam Question 115

    What is the best strategy for a LEED AP to suggest in order to quantify the impact of increasing the window-to-wall ratio on a Building Design and Construction project?