PMI-RMP Exam Question 96
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
PMI-RMP Exam Question 97
A stakeholder is asking a project team to hire an external vendor with more expertise and capacity to accelerate a delivery plan. The team has some concerns about this request. What should the risk manager do first?
PMI-RMP Exam Question 98
An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.
What should the risk owner do?
What should the risk owner do?
PMI-RMP Exam Question 99
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the project manager do next to determine risk impact of assumptions and constraints?
PMI-RMP Exam Question 100
What should the risk owner use as an effective information-gathering technique during the planning session?