PMP Exam Question 501

You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information:
Project Kansas City: The payback period is 27 months, and the IRR is 35 percent.
Project Spokane: The payback period is 25 months, and the IRR is 32 percent.
Which project should you recommend to the selection committee?
  • PMP Exam Question 502

    The data warehouse project is about halfway complete at a major retail client.
    Your company is doing the implementation and has twelve team members in various locations across three different buildings. Communication and team-building has been a real challenge. Which of the following would fix or improve this problem?
  • PMP Exam Question 503

    Key stakeholders disagree about the details in the project charter that describe how to deliver project requirements. What tool or technique should the project manager use to resolve this issue and obtain project charter approval?
  • PMP Exam Question 504

    A project manager completes a protect management plan for a global project due in 12 months. When two team members leave the project, what should the project manager do?
  • PMP Exam Question 505

    Achieving effective upward communications in an organization requires that the sender consider which of the following: