PMP Exam Question 506
During the first year of a three-year project a key supplier with a long lead time stops production and closes its factory. What should the project manager do first?
PMP Exam Question 507
The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing environment. Which of the following should concern the Project Manager the most?
PMP Exam Question 508
You have been assigned as project manager on what could be a "bet the company" project. You realize that to be successful you need to exercise maximum control over project resources. Which form of project organization should you establish for this project?
PMP Exam Question 509
You have just completed Qualitative Risk Analysis of the project. What should you be doing next?
PMP Exam Question 510
Which is not one of the triple constraint of a project?
