PMP Exam Question 506

During the first year of a three-year project a key supplier with a long lead time stops production and closes its factory. What should the project manager do first?
  • PMP Exam Question 507

    The sponsor on the airport runway project has just told the Project Manager about a change he wants. He says that the change will cost 20% less and should not cause any problems to the existing environment. Which of the following should concern the Project Manager the most?
  • PMP Exam Question 508

    You have been assigned as project manager on what could be a "bet the company" project. You realize that to be successful you need to exercise maximum control over project resources. Which form of project organization should you establish for this project?
  • PMP Exam Question 509

    You have just completed Qualitative Risk Analysis of the project. What should you be doing next?
  • PMP Exam Question 510

    Which is not one of the triple constraint of a project?