PMP Exam Question 86

A new team member inquires about how much they need to learn about the organizational process assets (OPAs) residing on the company intranet. Another team member states they only need to know the basics. However, the project manager believes the team member should know everything regarding the OPAs.
What should the project manager do?
  • PMP Exam Question 87

    You have been appointed project manager for a new project in your organization and must prepare a project management plan. You decide to prepare a WBS to show the magnitude and complexity of the work involved. No WBS templates are available to help you. To prepare the WBS, your first step should be to______________
  • PMP Exam Question 88

    The following is a network diagram for a project.

    How many possible paths are identified for this project?
  • PMP Exam Question 89

    Which of the following statements are true regarding random causes and special causes with respect to statistical Perform Quality Control?
  • PMP Exam Question 90

    The formalization of management's attitude toward risk is called _____ .