PMP Exam Question 101
A project manager in a matrix environment is struggling to keep the team fully engaged in the project. The team's line manager continually reprioritizes tasks, leading to delays and quality issues.
What should the project manager do?
What should the project manager do?
PMP Exam Question 102
An input to the Identify Risks process is the:
PMP Exam Question 103
The time necessary to complete a project is called the _______ of a project.
PMP Exam Question 104
You are project manager responsible for constructing a new sports arena for the upcoming
Olympics. Construction begins on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You've obtained the following measurements:
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5
You believe the type of variances that have occurred on the project to date are typical expect these variances to continue throughout the project. Based on the information above, what is the EAC for the project?
Olympics. Construction begins on a project over a year ago. The stakeholders of the project want a status report on the performance of the project to date. You've obtained the following measurements:
BAC=500, ETC=200, PV=500, AC=200, EV=300, CPI=1.5
You believe the type of variances that have occurred on the project to date are typical expect these variances to continue throughout the project. Based on the information above, what is the EAC for the project?
PMP Exam Question 105
To account for uncertainty in a schedule, reserve analysis may be used. All the following are examples of contingency reserves EXCEPT ______________