PMP Exam Question 156
A project manager needs to add a subject matter expert (SME) to the project team. However, no internal resources is available, so external resource will need to be hired.
What type of contract should be used?
What type of contract should be used?
PMP Exam Question 157
A customer is surprised about a change made to a deliverable. The project manager explains that this change was communicated via email, and that there is a possibility that the email has not yet been read What should the project manager have done differently?
PMP Exam Question 158
What is the total float of the critical path?
PMP Exam Question 159
A project manager is managing a two-year agile project with monthly iterations. The project manager identifies the following risk during project initiation: "Rapid development of new technologies used by the industries and stakeholders may reduce the delivered value." Which approach can the project manager use to mitigate the stated risk?
PMP Exam Question 160
You are a Project Manager who is involved in the procurement of $2,000,000 of infrastructure equipment.
As negotiations begin between your company and the vendor, you realize that your brother works for this company but in a different department. What is your professional and social responsibility?
As negotiations begin between your company and the vendor, you realize that your brother works for this company but in a different department. What is your professional and social responsibility?