PMP Exam Question 156

A project manager needs to add a subject matter expert (SME) to the project team. However, no internal resources is available, so external resource will need to be hired.
What type of contract should be used?
  • PMP Exam Question 157

    A customer is surprised about a change made to a deliverable. The project manager explains that this change was communicated via email, and that there is a possibility that the email has not yet been read What should the project manager have done differently?
  • PMP Exam Question 158

    What is the total float of the critical path?
  • PMP Exam Question 159

    A project manager is managing a two-year agile project with monthly iterations. The project manager identifies the following risk during project initiation: "Rapid development of new technologies used by the industries and stakeholders may reduce the delivered value." Which approach can the project manager use to mitigate the stated risk?
  • PMP Exam Question 160

    You are a Project Manager who is involved in the procurement of $2,000,000 of infrastructure equipment.
    As negotiations begin between your company and the vendor, you realize that your brother works for this company but in a different department. What is your professional and social responsibility?