PMP Exam Question 191

An impact assessment reveals that a deliverable could delayed by two weeks. A key resource has not been available to work one a non-critical activity due to other priorities. This could cause work overload on the remaining resources.
Since cost is a major constrain for this project, what should the project manager do immediately?
Determine if the task has available float to meet the project end date.
  • PMP Exam Question 192

    You have contracted some work to a sub-contractor and would like to identify successes and failures of other procurement contracts within the performing organization. This can be performed through:
  • PMP Exam Question 193

    All of the statements regarding decision tree analysis is true EXCEPT:
  • PMP Exam Question 194

    A project manager discover that material costs have increased significantly since project initiation. To what should the project manager refer to determine if the project is still feasible.
  • PMP Exam Question 195

    Faulty vendor-supplied parts must be returned and reordered. Based on previous experiences with this vendor, the project team had already identified this as a risk.
    What should the project manager do to record this?