PMP Exam Question 171

The scope management plan is a subsidiary of which project document?
  • PMP Exam Question 172

    Which of the following best describes the complete set of indexed contract documentation, including the closed contract, for inclusion with the final project file?
  • PMP Exam Question 173

    Two weeks ago the project manager was fired for not managing the project well. The project is behind schedule, over cost and the morale on the team is very low. The new project manager is having a team meeting. She starts out by telling the team about the last three projects she worked on, how they were similar to this one and how she brought them in ahead of schedule and on budget. What type of power is she establishing?
  • PMP Exam Question 174

    When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
  • PMP Exam Question 175

    Which of the following best describes a conflict resolution technique the temporarily solves a problem by downplaying the problem to make the problem appear less important/ critical?