PMP Exam Question 41
You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in?
PMP Exam Question 42
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
PMP Exam Question 43
Rank ordering of defects should be used to guide corrective action. This is the underlying principle behind______________
PMP Exam Question 44
An organization's objectives require the reduction of costs associated with future failures What should the project manager do when budgeting cost?
PMP Exam Question 45
The Process Group in which the internal and external stakeholders interact and influence the overall outcome of the project is the: