PMP Exam Question 26

Who should contribute to the development of the project plan?
  • PMP Exam Question 27

    Ateam lead for a project that is currently in execution with multiple delivery teams is issuing status updates.
    This communication was not discussed with the project manager, and the project stakeholders areconcerned about nonalignment since other teams are not providing these updates.
    What should the project manager do?
  • PMP Exam Question 28

    A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
  • PMP Exam Question 29

    Paul is a project manager for an industrial design project. The project has a 60% chance of making the company $230,000 over the next year. It has a 40% chance of costing the company $150,000. What's the project's EMV?
  • PMP Exam Question 30

    The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?