PMP Exam Question 31

Your hardware vendor left you a voicemail saying that a snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and
asked that you return the call. Which of the following statements is true? (Choose the best answer.)
  • PMP Exam Question 32

    Which of the following calculates the difference between the budget at completion and estimate at completion?
  • PMP Exam Question 33

    A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

    PMP Exam Question 34

    Project managers should pay attention to critical and subcritical activities when evaluating project time performance. One way to do this is to analyze 10 sub critical paths in order of ascending float. This approach is part of______________
  • PMP Exam Question 35

    In the Initiating Process Group, at what point does the project become officially authorized?