PMP Exam Question 641

The project manager has finished all the tasks of the project and immediately starts on a new project. A few months after beginning the new project, the accounting manager asks for confirmation of previous projects because the budget is still open with no further cash flows.
What should the project manager have done?
  • PMP Exam Question 642

    A project's budgeted value of work completed is less than the authorized budget for planned work. What project scenario does this describe?
  • PMP Exam Question 643

    A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards What should the project manager do?
  • PMP Exam Question 644

    A transportation company is developing a new tool to improve their delivery process. As project development for sprint two began, the executive steering committee made a request to include a new capability to perform a what-if analysis in the tool based on the customer demand and forecast.
    What should the project manager do next?
  • PMP Exam Question 645

    As project manager, you identified a number of acceptable tolerances as part of your earned value management system. During execution, some "unacceptable" variances occurred. After each "unacceptable" variance occurred, you did which one of the following first?