PMP Exam Question 631
Which of the following are the essentials regarding a project close-out? (Choose all that apply.)
PMP Exam Question 632
You are in the process of controlling changes to project cost baseline. Which of the following is the LEAST helpful input?
PMP Exam Question 633
Issue change requests and adapt approved changes into the project's scope, plans, and environment is an activity included in which of the following project management processes?
PMP Exam Question 634
A project manager who recently joined the company has been assigned to manage a software project for a major recurring customer. What should the project manager do to enhance the budget estimations for the project?
PMP Exam Question 635
A project manager has received an updated earned value analysis report. The following are the key findings from the report:
* Budget at completion = US$1 million
* Earned value = US$0,7 million
* Actual cost = US$0,75 million
* Cost performance index = 0,933
Based on this information, what should the project manager conclude about project performance?
* Budget at completion = US$1 million
* Earned value = US$0,7 million
* Actual cost = US$0,75 million
* Cost performance index = 0,933
Based on this information, what should the project manager conclude about project performance?