PMP Exam Question 626
A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence.
What shouldthe project manager do?
What shouldthe project manager do?
PMP Exam Question 627
You are in the process of identifying and documenting project risks. Which of the following is the LEAST helpful tool/ technique?
PMP Exam Question 628
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support.
What should the project manager do next?
What should the project manager do next?
PMP Exam Question 629
What are assigned risk ratings based upon?
PMP Exam Question 630
A multinational project includes stakeholders from various locations and cultures During the final acceptance stage a new stakeholder is added who refuses to provide final approval.
What should the project manager do?
What should the project manager do?