PMP Exam Question 626

A risk was raised during the initiation of a project. The supplier discontinued software support for one of the project's required inputs. The project manager planned a reserve budget to allow the project to continue in the event of this occurrence.
What shouldthe project manager do?
  • PMP Exam Question 627

    You are in the process of identifying and documenting project risks. Which of the following is the LEAST helpful tool/ technique?
  • PMP Exam Question 628

    A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support.
    What should the project manager do next?
  • PMP Exam Question 629

    What are assigned risk ratings based upon?
  • PMP Exam Question 630

    A multinational project includes stakeholders from various locations and cultures During the final acceptance stage a new stakeholder is added who refuses to provide final approval.
    What should the project manager do?